Investment & Payment Milestones

Program budget by component and milestone-based payment schedule across the 44-week engagement.

Total program investment
0.0%
$2.38M
Invoiced to date
0.0%
$1.07M
Milestones cleared
0.0%
3/7
Forecast ROI · 18mo
0.4%
5x

Cost by component

Investment allocation across the eight phases

Discovery & Strategy$120K · 5%
Monetization Engine$380K · 16%
ROI Intelligence Platform$260K · 11%
Vertical Solutions$420K · 18%
Marketplace Platform$360K · 15%
Data Fabric Layer$340K · 14%
Cost Optimization Engine$240K · 10%
Testing & Deployment$260K · 11%

Payment milestones

Schedule tied to phase-gate approvals

MilestoneTargetShareAmountStatus
Project KickoffW015%$357KPaid
Phase 1 CompletionW410%$238KPaid
Phases 2–3 CompletionW1820%$476KPaid
Phase 4 CompletionW2815%$357KIn Progress
Phase 5 CompletionW3615%$357KScheduled
Phases 6–7 CompletionW4215%$357KScheduled
Go-LiveW4410%$238KScheduled